“The internal review, disclosed under freedom of information laws, reveals that instead of producing the predicted 120 tons of fuel a year to sell to foreign power companies, the Sellafield MOX plant (SMP) managed to yield a total of less than 14 tons in 10 years. When the plant was shut down in 2011 it had cost £1.4bn, compared to the £280m estimated when the plant was approved in 1993.”

 

Revealed: £2bn cost of failed Sellafield plant

 

Internal review deals blow to the Government’s hope of commissioning new mixed-oxide facility

 

BRIAN BRADY    SUNDAY 09 JUNE 2013

 

http://www.independent.co.uk/news/uk/politics/revealed-2bn-cost-of-failed-sellafield-plant-8650779.html