Failed Sellafield plant
“The internal review, disclosed under freedom of information laws, reveals that instead of producing the predicted 120 tons of fuel a year to sell to foreign power companies, the Sellafield MOX plant (SMP) managed to yield a total of less than 14 tons in 10 years. When the plant was shut down in 2011 it had cost £1.4bn, compared to the £280m estimated when the plant was approved in 1993.”
Revealed: £2bn cost of failed Sellafield plant
Internal review deals blow to the Government’s hope of commissioning new mixed-oxide facility
BRIAN BRADY SUNDAY 09 JUNE 2013